REPORT - PARKING GARAGE 9 - 2017 REPAIR PROJECT
BACKGROUND: The Parking Garage 9 - 2017 Repair Project arises from a recommendation received by the City in a condition appraisal report prepared by Walker Restoration Consultants, dated March 2007. The most significant deficiency to be addressed by the proposed project involves replacement of the top layer of concrete (the “wear slab”) on the top level of Garage 9. Other work includes selective concrete repair, crack sealing and waterproofing. The repairs will protect structural components and extend the service life of the parking garage.
On September 4, 2018, an award of Contract No. C01823 to Ashron Construction and Restoration, Inc., of Santa Clara, California was presented to the City Council for consideration. The motion to award the contract resulted in a tie vote (3 ayes, 3 noes). The Council thereafter directed staff to bring back a smaller scale repair project and wait a year to bring back a project for full repairs. Th...
|