Title:
|
REPORT - SUBCONTRACTOR ADDITION - LAGUNA TREATMENT PLANT CHILLERS AND CLIMATE CONTROL UPGRADES AT ADMINISTRATION AND ANNEX BUILDING
BACKGROUND: The Laguna Treatment Plant Chillers and Climate Control Upgrades at Administration and Annex Buildings project (Project) will consist of the replacement of two 50-ton chillers and two condensing boilers in the Administration building, and one 15-ton chiller at the Annex building. The Project will also provide upgrades of the climate control system at both buildings. On October 17, 2019, the Board of Public Utilities, by motion, approved construction Contract No. C02105 in the amount of $1,004,198.40 to the lowest responsive bidder, Matrix HG, Inc., of Novato, CA for Laguna Treatment Plant Chillers and Climate Control Upgrades at Administration and Annex Building. Matrix subsequently submitted a request for Wunderlich-Malec Engineering (WM) to be added to the Contract as a subcontractor responsible for the PLC panel building, programming, test...
|