Title:
|
REPORT - RESOLUTION OF THE BOARD OF PUBLIC UTILITIES APPROVING THE USACE PARTNERSHIP AGREEMENT FOR INCREMENT 1 OF THE LLANO TRUNK REHABILITATION PHASE 2 PROJECT AND DELEGATING AUTHORITY TO THE DIRECTOR OF WATER
BACKGROUND: The Llano Trunk Line Rehabilitation Phase 2 Environmental Infrastructure Project (‘Project”) was identified as the second priority trunk lining project in the 2023 Sanitary Sewer Master Plan Update. The Department of the Army’s United States Army Corp of Engineers (USACE) is partnering with the City of Santa Rosa to deliver the project in five phases and five corresponding increments of funding. Increment 1 would be provided under the subject Agreement Between the Department of the Army and the City of Santa Rosa for Design and Construction Assistance for the Llano Trunk Line Rehabilitation Phase 2 Environmental Infrastructure Project (“Partnership Agreement”).
This Resolution approves the Partnership Agreement for Increment 1 of the Project and delegates authority...
|