Title:
|
REPORT - AUTHORITY TO ISSUE DESIGN-BUILD REQUEST FOR PROPOSALS FOR THE LLANO TRUNK REHABILITATION PHASE 1
BACKGROUND: As part of the 2021 Sanitary Sewer Master Plan Update, engineering consulting firm Woodard and Curran inspected and assessed approximately 13 miles of large diameter trunk sewers that are part of the City’s collection system to establish rehabilitation and replacement priorities. Nearing the end of its useful life and exhibiting a high risk of failure, sections of the Llano trunk were identified as the highest priority with a recommendation for rehabilitation within one to two years.
Utilization of a Design-Build (DB) delivery method could provide the City with the best-qualified DB entity and expedite project delivery through increased collaboration between the engineer, contractor, and City during the design and permitting phases.
RECOMMENDATION: It is recommended by the Transportation and Public Works Department and the Water Department that the Board of Public ...
|
|
Code sections:
|
15302(c) - Replacement or Reconstruction
|