Title:
|
REPORT - US HIGHWAY 101 - BICYCLE AND PEDESTRIAN BRIDGE ADDITIONAL ALTERNATIVE EVALUATION
BACKGROUND: In June 2017, BKF was hired to complete the Project Approval and Environmental Document (PA&ED) phase, required by Caltrans, and to prepare the environmental document with a detailed analysis for the Edwards Avenue-Elliott Avenue bridge alignment. Santa Rosa Junior College is now a willing partner with the city and open to discussion about relinquishing right of way if needed to make the project a reality.
RECOMMENDATION: It is recommended by the Transportation and Public Works Department that the Council, by resolution, approve Amendment No. 1 to Project Work Order No. A010119-2016-01, with BKF Engineers, of Pleasanton, CA for the US Highway 101 - Bicycle and Pedestrian Bridge Project (Proposed Project), Project Report and Environmental Documentation (PA&ED) to evaluate an additional project location, the Range Avenue-Bear Cub Way alignment, increasing the contract amount by $379,34...
|