Title:
|
REPORT - PROJECT WORK ORDER AMENDMENT NO. 5 APPROVAL - ENGINEERING SERVICES DURING CONSTRUCTION AND REGULATORY COMPLIANCE SUPPORT FOR CONSTRUCTION OF THE LAGUNA TREATMENT PLANT DISINFECTION IMPROVEMENTS PROJECT WITH CAROLLO ENGINEERS
BACKGROUND: This proposed action will approve Project Work Order (PWO) Amendment No. 5 in the amount of $1,170,989 to PWO No. A010014-2011-09 under the Master Professional Services Agreement with Carollo Engineers, Inc. of Walnut Creek to provide additional Engineering Services During Construction (ESDC) and regulatory compliance support during construction of the Laguna Treatment Plant Disinfection Improvements Project.
Due to a longer construction duration than was contemplated when Carollo’s original ESDC scope was developed for PWO Amendment 2 (A010014-2011-09B), in addition to a greater number of submittals, design clarifications, and requests for information during construction than was anticipated, the City needs to amend the existing PWO to incr...
|
Indexes:
|
Environmental Impact Report Certified
|
Code sections:
|
15162 - Subsequent EIR and Negative Declarations, 15164 - Addendum to an EIR or Negative Declaration
|