REPORT - COURTHOUSE SQUARE REUNIFICATION PROJECT UPDATE, EXPENDITURE REPORT AND CONTINGENCY ACTION
BACKGROUND: This item will update the Council on the progress of the Courthouse Square Reunification project and provide information regarding expenditures for construction, construction management/inspection, and contingency. Council action is recommended to approve additional construction contingency needed to complete the project as a result of upgrades to the electrical facilities.
RECOMMENDATION: It is recommended by the Transportation and Public Works Department that the Council, by motion, accept the Courthouse Square Reunification expenditure report and approve additional construction contingency in the amount of $250,000 for electrical facility upgrades.
|
Indexes:
|
EIR Previously Certified by City Council
|