Title:
|
REPORT - PROJECT WORK ORDER APPROVAL - PROFESSIONAL ENGINEERING SERVICES FOR FARMERS LANE GROUNDWATER WELL FACILITY EVALUATION PHASE 2
BACKGROUND: The Farmer’s Lane Well Facility upgrades evaluation has entered into the design phase for the well rehabilitation and repairs. The current budget does not account for geotechnical, structural and electrical design costs needed to complete the design for reconstructing the well houses; ensuring climate control for electrical equipment; and providing security and aesthetics at these facilities. The additional budget requested is $106,700.00, increasing the total budget to $571,900.00.
RECOMMENDATION: It is recommended by the Water Department and the Transportation and Public Works Department, that the Board, by motion, approve a Project Work Order (PWO) under the Master Professional Services Agreement with West Yost & Associates, Inc. of Pleasanton, California, to provide Professional Engineering Services for Farmers Lane Groundwater Wel...
|