Title:
|
MOTION - REQUEST FOR ADDITIONAL CONTRACT CONTINGENCY - FARMERS LANE WELL FACILITY REHABILITATION
RECOMMENDATION: It is recommended by the Transportation and Public Works Department and the Water Department that the Board, by motion, approve additional contingency for Contractor to remove a newly installed air conditioning unit from Well House W-2, repair damages to the building that result from the removal, and install a new, more robust air conditioning unit to replace what was removed. The estimated cost of the work and additional 10% contingency is $34,450.00.
|