Title:
|
RESOLUTION - REQUEST FOR APPROVAL OF ADDITIONAL CONTRACT CONTINGENCY - DONAHUE, DECKER, BOYCE & PETALUMA HILL SEWER AND WATER MAIN IMPROVEMENTS
RECOMMENDATION: It is recommended by the Transportation and Public Works Department and the Water Department that the Board of Public Utilities, by motion, approve a 10% increase in contingency from 15% to 25% for the additional contaminated soil disposal, extra costs to resolve utility conflicts, and additional roadway resurfacing for a total contingency of $316,169.49, and contract amount of $1,580,847.46.
|