Title:
|
REPORT - APPROVAL OF PROFESSIONAL SERVICES AGREEMENT - ENGINEERING DESIGN - LAGUNA TREATMENT PLANT ELECTRICAL INFRASTRUCTURE IMPROVEMENTS PROJECT
BACKGROUND: This motion will approve a Professional Services Agreement (PSA) with Hazen and Sawyer to provide engineering design for the Laguna Treatment Plant Electrical Infrastructure Improvements Project, for a total authorized amount of $2,552,847.
RECOMMENDATION: It is recommended by the Contract Review Subcommittee of the Board, the Transportation and Public Works Department and Santa Rosa Water that the Board of Public Utilities (Board), by motion, approve a Professional Services Agreement with Hazen and Sawyer to provide engineering design for the Laguna Treatment Plant Electrical Infrastructure Improvements Project, for a total authorized amount of $2,552,847.
|
Indexes:
|
Mitigated Negative Declaration
|