Title:
|
REPORT - APPROVAL OF AMENDMENT NO. 2 TO PROJECT WORK ORDER WITH GREEN VALLEY CONSULTING ENGINEERS - EMERGENCY WELL PUMP STATION - A PLACE TO PLAY - CONSTRUCTION MANAGEMENT AND INSPECTION
BACKGROUND: The A Place To Play well project includes the conversion of an existing test well to an emergency ground water well and pump station. Construction began in July 2020 with a design based on past water quality data that was obtained when the well was initially constructed. As construction on the conversion and pump station progressed, subsequent water sampling analyses detected arsenic levels above the State maximum contaminant level (MCL) for public drinking water supplies. Construction was suspended in November 2020 to explore water treatment options that would reduce the arsenic concentrations below the regulatory limit.
Construction commenced February 2022, and progressed until November of 2022, when an electrical material procurement delay caused the project to fall into suspension. Co...
|
|
Indexes:
|
Exempt Project, Mitigated Negative Declaration Previously Adopted
|
|
Code sections:
|
15303 - New Construction or Conversion of Small Structures
|