Title:
|
MOTION - HEARN COMMUNITY HUB PHASE 1 - DESIGN BUILD CONTRACT COST AMENDMENT ACTION AND BUDGET AMENDMENT
RECOMMENDATION: It is recommended by the Transportation and Public Works Department that the Council, by motion, approve an additional contingency of $2,396,375 for the Hearn Community Hub Phase 1 Project, Contract Number C02412, with best value Design-Build entity, Swinerton Incorporated of Sacramento, California, resulting in a total approved contingency of $4,396,375 and a total authorized contract amount of $35,396,375.
|